Completed Construction - October 1st, 2020

Project duration 15 Months

Unit 1

The Linden - A Brand-New Living Experience.

Unit 3

The Linden - Comprised of six 3-story townhouse communities, each with five studios and a spacious, central lounge and kitchen.

Exterior

Staging and Landscaping - July 8th, 2020

Project Duration - 13.5 Months

Staging and Landscaping - June 16th, 2020

Project Duration - 12.5 Months

Flooring and cabinet Install - May 16th, 2020

Project Duration - 11.5 Months

Virtual Tour

Interior Paint, Cabinet and Tile Install - March 26th, 2020

Project Duration - 10.0 Months

Exterior Paint, Dry Wall and Mudding - January 17th, 2020

Project Duration - 9.0 Months

Exterior Paint and Dry Wall Install - January 17th, 2020

Project Duration - 8.0 Months

Facade and Windows Completed - December 16th, 2019

Project Duration - 7.0 Months

Facade Started - November 15th, 2019

Project Duration - 6.0 Months

Roofing Started - October 22nd, 2019

Project Duration - 5.5 Months

Framing Complete - October 8th, 2019

Project Duration - 5 Months

Framing - September 8th, 2019

Project Duration - 4 Months

Framing - August 23rd, 2019

Project Duration - 3.5 Months

Concrete Pour- July 25th, 2019

Project Duration - 2.5 Months

Framing Status - July 9th, 2019

Project Duration - 2 Months

Concrete Pour- June 20th, 2019

Project Duration - 1 Month

Breaking Ground- June 6th, 2019

Project Duration - .5 Month

 18th and Linden Start, May 15th 2019