2618 MLK

 

Project Completed - June 29th, 2021

Project Duration - 17.5 Months

Building 3 cabinets installed, building 2 staging arrival, building 1 staged - May 29th, 2021

Project Duration - 16.5 Months

Building 3 drywalled, building cabinet install, and staging in building 1 - April 26th, 2021

Project Duration - 15.5 Months

Building 3 drywalled, building cabinet install, and cabinet staging in building 1 - March 20th, 2021

Project Duration - 14.5 Months

Building 3 insulated, building 2 painted, and cabinet install in building 1 - January 29th, 2021

Project Duration - 13.5 Months

Building 3 framed, building 2 drywalled, and cabinet install in building 1 - December 28th, 2020

Project Duration - 12.5 Months

Cabinet and Roofing install - September 28th, 2020

Project Duration - 9.5 Months

Insulation and electrical install - July 8th, 2020

Project Duration - 7.0 Months

Additional Framing and Electrical Installed - June 16th, 2020

Project Duration - 6.5 Months

Additional Building Frames Installed - May 16th, 2020

Project Duration - 5.5 Months

Concrete Frames and Additional Levels Installed - March 26th, 2020

Project Duration - 4.0 Months

Frame Installation - February 13th, 2020

Project Duration - 3.0 Months

Foundation Frame Installed - January 17th, 2020

Project Duration - 2.0 Months

Utility Install - December 16th, 2019

Project Duration - 1 Month

Breaking Ground - November 25th, 2019

Project Duration - .5 Month