Staging/Project Complete - March 05th, 2022

Project Duration - 13.0 Months

Appliance Install - December 29th, 2021

Project Duration - 11.0 Months

Interior/Exterior paint - November 29th, 2021

Project Duration - 10.0 Months

Interior/Exterior paint - October 29th, 2021

Project Duration - 9.0 Months

flooring and cabinet install - September 1st, 2021

Project Duration - 8.0 Months

Insulation Install - June 29th, 2021

Project Duration - 5.5 Months

Electrical & Plumbing Install - May 29th, 2021

Project Duration - 4.5 Months

Electrical Install & Foundation Retrofitting - March 20th, 2021

Project Duration - 3.5 Months

Interior Framing & Foundation Retrofitting - March 20th, 2021

Project Duration - 3.5 Months

Interior Framing - January 29th, 2021

Project Duration - 2 Months

Demo - January 5th, 2021

Project Duration - 1 Month