MANDELA 1705

Mural Painting

Project Complete - July, 2022

Project Duration - 17.5 Months

Countertops & Appliance Install - June, 2022

Project Duration - 16.5 Months

Exterior Mural & Flooring Install - May, 2022

Project Duration - 15.5 Months

Cabinet Install - April, 2022

Project Duration - 14.5 Months

Window Install- Dec 29th, 2021

Project Duration - 10.5 Months

Drywall Install- Nov 29th, 2021

Project Duration - 9.5 Months

Framing Second Floor - June 29th, 2021

Project Duration - 4.5 Months

Framing - May 29th, 2021

Project Duration - 3.5 Months

Concrete Pour - May 1st, 2021

Project Duration - 2.5 Months

Foundation Framing Start - March 20th, 2021

Project Duration - 1.5 Months

Breaking Ground - January 29th, 2021

Project Duration - 0.5 Month